Long-term stability analysis of large-scale underground plant ofXiangjiaba hydro-power station

来源期刊:中南大学学报(英文版)2011年第2期

论文作者:徐卫亚 聂卫平 周先齐 石崇 王伟 冯树荣

文章页码:511 - 520

Key words:large-scale underground plant; rheological mechanics; optimal supporting time; maximum creep deformation; long-term stability; long-term strength

Abstract: Numerical analysis of the optimal supporting time and long-term stability index of the surrounding rocks in the underground plant of Xiangjiaba hydro-power station was carried out based on the rheological theory. Firstly, the mechanical parameters of each rock group were identified from the experimental data; secondly, the rheological calculation and analysis for the cavern in stepped excavation without supporting were made; finally, the optimal time for supporting at the characteristic point in a typical section was obtained while the creep rate and displacement after each excavation step has satisfied the criterion of the optimal supporting time. Excavation was repeated when the optimal time for supporting was identified, and the long-term stability creep time and the maximum creep deformation of the characteristic point were determined in accordance with the criterion of long-term stability index. It is shown that the optimal supporting time of the characteristic point in the underground plant of Xiangjiaba hydro-power station is 5-8 d, the long-term stability time of the typical section is 126 d, and the corresponding largest creep deformation is 24.30 mm. While the cavern is supported, the cavern deformation is significantly reduced and the stress states of the surrounding rock masses are remarkably improved.

有色金属在线官网  |   会议  |   在线投稿  |   购买纸书  |   科技图书馆

中南大学出版社 技术支持 版权声明   电话:0731-88830515 88830516   传真:0731-88710482   Email:administrator@cnnmol.com

互联网出版许可证:(署)网出证(京)字第342号   京ICP备17050991号-6      京公网安备11010802042557号